Council District 7
D7 Projects
Active infrastructure and safety projects underway in District 7. Find what is being built, what is out to bid and what is still in design, and how it affects your commute.
Community priorities
Power Santa Clara Valley Utility Project
A new underground electric connection between South San José and Downtown San José. Construction began in May 2026 and continues on Monterey Road between Capitol Expressway and West Alma Avenue into 2027.
View project page →SafetyEast Alma Avenue Safety Improvement Project
Repaving, protected bike lanes, and crosswalk upgrades between Monterey Road and Senter Road. Planning and community outreach underway.
View project page →TransportationSenter Road Earmark Project
New signal, transit amenities, lighting, and protected bike lanes along the corridor. Under construction, expected to wrap up January 2027.
View project page →Coming up
- This monthConstruction starts on the Central Service Yard Fuel Island.
- OctoberFire Station No. 32 expects its Temporary Occupancy Certificate.
- Oct 27Targeted City Council date for the Elia Park contract award.
- Late OctTully Road Bridge repairs begin, along with three sewer repair packages.
- Mid to late NovTully and Balfour intersection work on Senter Road expected to wrap up.
- DecemberElia Park construction begins; Senter Road Vision Zero improvements expected to finish.
City capital projects in District 7
Managed by the City of San José Department of Public Works. Choose a phase, pick a project type or search by street, park or project name.
Public Safety and City Facilities
Fire stations, emergency operations and City buildings.
Fire Station No. 32 (New)
A new dual company fire station with two apparatus bays, funded by 2018 Measure T.
- Design
- Bid & Award
- Construction
- Contract
- $12.9M
- Began
- Aug 2024
- Finish
- Sep 2026
District 7
Project details
Latest update
Construction is about 98% complete and most of the remaining work is site work. The project expects to receive a Temporary Occupancy Certificate in October 2026.
About the project
A new dual company, one story fire station at 1138 Olinder Ave (Olinder Court at Felipe Avenue) on a site of about 1.12 acres. The 8,100 square foot building has a two vehicle bay large enough to house a tiller vehicle. Site work includes parking for staff and the public, an onsite generator and diesel tank, perimeter fencing, and landscaping with bioretention areas. Demolition, soil mitigation and rough grading were completed on June 6, 2023.
Location
1138 Olinder Court, San José, CA 95112
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | May 2021 | Actual |
|---|---|---|
| Design completion | December 2022 | Actual |
| Award | June 2024 | Actual |
| Construction start | August 2024 | Actual |
| Beneficial use | September 2026 | Scheduled |
Central Service Yard Fuel Island
A new fuel island with diesel, unleaded and DEF tanks and a canopy.
- Design
- Bid & Award
- Construction
- Contract
- $3.1M
- Starts
- Sep 2026
- Finish
- Nov 2027
District 7
Project details
Latest update
The construction contract with W.E. Lyons was executed on September 11, 2026.
About the project
New construction of a fuel island at the Central Service Yard that includes diesel, unleaded and diesel exhaust fluid (DEF) aboveground storage tanks and a fuel island canopy.
Location
Central Service Yard, 1661 Senter Road, San José, CA 95112
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | June 2023 | Actual |
|---|---|---|
| Design completion | May 2025 | Actual |
| Award | July 2026 | Actual |
| Construction start | September 2026 | Scheduled |
| Beneficial use | November 2027 | Scheduled |
Fire Station No. 36 (New)
A new single company fire station at Tuers Road and East Capitol Expressway, funded by 2018 Measure T.
- Design
- Bid & Award
- Construction
- Estimate
- $16.5M
- Starts
- Aug 2027
- Finish
- Apr 2029
District 7
Project details
Latest update
Consultants have finished the 50% construction documents and moved into the City plan check set phase. They are coordinating with subconsultants and utility agencies. The City will prequalify contractors before bidding, with bid advertisement scheduled for February 2027.
About the project
Construction of a new single company fire station.
Location
Tuers Road and East Capitol Expressway
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | March 2025 | Actual |
|---|---|---|
| Design completion | February 2027 | Scheduled |
| Award | May 2027 | Scheduled |
| Construction start | August 2027 | Scheduled |
| Beneficial use | April 2029 | Scheduled |
Fire Training Center and Emergency Operations Center HVAC Improvements
Evaluation and replacement of heating and cooling systems at two critical public safety facilities.
- Design
- Bid & Award
- Construction
- Estimate
- $4.2M
- Starts
- Aug 2027
- Finish
- Aug 2028
District 7
Project details
Latest update
The City has engaged IMEG Corp. for design services. The project is entering the design phase, which will set the detailed scope and requirements for the next stage.
About the project
The project evaluates the condition, performance, reliability and operational needs of the existing HVAC systems at the Emergency Operations Center and the Fire Training Center. Based on that evaluation, it will design system replacements and recommended improvements to boost reliability, energy efficiency and long term functionality, supporting safe and uninterrupted operations at both facilities.
Location
1591 Senter Road, San José, CA 95112
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | October 2026 | Scheduled |
|---|---|---|
| Design completion | April 2027 | Scheduled |
| Award | July 2027 | Scheduled |
| Construction start | August 2027 | Scheduled |
| Beneficial use | August 2028 | Scheduled |
San José Charge
DC fast charging hubs at five City facilities, built and operated by developer MN8.
- Design
- Bid & Award
- Construction
- Estimate
- Not listed
- Starts
- Jan 2027
- Finish
- Aug 2027
Districts 3, 7, 8
Project details
Latest update
The contract with developer MN8 has been executed. MN8 is conducting preliminary design to be submitted for Public Works review.
About the project
City Council approved procuring a developer to design, install, operate and maintain DC fast charging hubs at five City facilities. MN8 was selected as the project developer. Public Works will lead the permitting and construction phases.
Location
Evergreen Library, 2635 Aborn Rd. Market Street Garage, 45 N Market St. Rancho del Pueblo Golf Course, 1649 Hermocilla Way. Tully Library, 880 Tully Rd. Seven Trees Community Center, 3590 Cas Dr.
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | May 2026 | Actual |
|---|---|---|
| Design completion | December 2026 | Scheduled |
| Award | January 2027 | Scheduled |
| Construction start | January 2027 | Scheduled |
| Beneficial use | August 2027 | Scheduled |
Parks
New and improved parks, play areas and open space.
Happy Hollow Park & Zoo: Fossa Night House Phase 2
Phase 2 of a new night house for the Fossa exhibit at Happy Hollow Park & Zoo.
- Design
- Bid & Award
- Construction
- Contract
- $798,600
- Began
- May 2026
- Finish
- Sep 2026
District 7
Project details
Latest update
The contract with S&H Construction was executed on May 12, 2026. The CMU wall, roof framing, blocking, ceiling panels, siding, interior and exterior animal enclosures, netting, plumbing and painting are complete. Electrical is nearly complete. Construction was expected to finish on September 25, 2026. The September 24 report does not yet confirm completion.
About the project
Phase 2 continuation of construction of a new night house for the Fossa exhibit. The improvements are required by the Association of Zoos & Aquariums.
Location
Happy Hollow Park & Zoo, 1300 Senter Road
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | December 2025 | Actual |
|---|---|---|
| Design completion | April 2026 | Actual |
| Award | March 2026 | Actual |
| Construction start | May 2026 | Actual |
| Beneficial use | September 2026 | Scheduled |
Elia Park
A new 0.33 acre park at the corner of West Alma and Sanborn Avenues, next to the Alma Community Center.
- Design
- Bid & Award
- Construction
- Contract
- $2.8M
- Starts
- Dec 2026
- Finish
- Sep 2027
District 7
Project details
Latest update
The project received six bids on July 30. QLM, Inc. was determined to be the lowest responsive and responsible bidder, and a Notice of Intent to Award was issued on August 4. Staff is preparing a Council memo in response to a protest and is targeting the October 27 City Council meeting. Award is anticipated in October, with construction expected to begin in December 2026.
About the project
Design and construction of a 0.33 acre park. Scope includes demolition of two single story structures and soil remediation, replacement of sidewalk, driveway, curb ramp, curbs and gutters in the public right of way, and construction of new play equipment, a shade structure, perimeter fencing and walls, paving, seat walls, furnishings, park lighting, signage, irrigation and plantings.
Location
1413 Sanborn Avenue and 100 to 104 W. Alma Avenue, southwest corner of W. Alma and Sanborn, adjacent to the Alma Community Center
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | September 2025 | Actual |
|---|---|---|
| Design completion | June 2026 | Actual |
| Award | October 2026 | Scheduled |
| Construction start | December 2026 | Scheduled |
| Beneficial use | September 2027 | Scheduled |
Communications Hill Dog Park (Turnkey Park, Phase 3)
A fenced dog park with separate large and small dog areas on Communications Hill.
- Design
- Bid & Award
- Construction
- Estimate
- $2.2M
- Schedule
- TBA
District 7
Project details
Latest update
The City's comments on the 95% construction documents were sent to the developer.
About the project
A large and small fenced dog park with double gate entry systems. The scope also includes site furnishings including tables and chairs, trash receptacles, benches and bike racks.
Location
Communications Hill Boulevard and Joseph Borba Street
Location map
Map from the City of San José CIP report.
Schedule
A schedule has not been published yet.
Azevedo Park (Turnkey Park, Communications Hill Phase 4)
A new park with a central turf area, plazas and paths on Communications Hill.
- Design
- Bid & Award
- Construction
- Estimate
- $3.0M
- Schedule
- TBA
District 7
Project details
Latest update
The City's comments on the 95% construction documents were sent to the developer.
About the project
Scope includes a large central turf area, concrete circulation paths, granitecrete and concrete plazas, and site furnishings. The park will also include new planting and irrigation.
Location
Thomas Kell Place and Kell Ranch Street
Location map
Map from the City of San José CIP report.
Schedule
A schedule has not been published yet.
Streets, Bikeways and Safety
Complete streets, bus improvements and lighting.
Vision Zero East San José Safety Improvements: Senter Road
Protected bike lanes, bus islands, radar signs, new streetlights and a new signal at Balfour along 4.7 miles of Senter Road.
- Design
- Bid & Award
- Construction
- Contract
- $6.9M
- Began
- Apr 2026
- Finish
- Dec 2026
Districts 2, 7
Project details
Latest update
Tully and Senter is 70% complete, expected through mid November 2026. Concrete work and asphalt bike lanes are done on all four corners, utility companies are moving facilities to new grade, and storm drain work at the southeast and southwest corners is finished. Balfour and Senter is 50% complete, expected through late November 2026. Electrical work is done at the northeast and southeast corners and the contractor is preparing to pour sidewalk and ramp at those corners.
About the project
Funds key pedestrian, bicyclist and transit safety improvements along 4.7 miles of Senter Road between Story Road and Monterey Road: speed radar signs, enhanced crosswalks with flashing beacons, concrete curbs to protect bike lanes, planted median islands, advanced pedestrian and bike sensors, bus boarding islands, transit signal priority, new streetlights and a new traffic signal at Balfour Road. Initial allocations: $2.35M for LED streetlights and pedestrian scale lights, $1.5M for a concrete curb barrier protecting the new Class IV buffered bike lane, $2.5M for a new signal at Senter and Balfour, and $1.1M for bus boarding islands, shelters and benches.
Location
Senter Road from Keyes Street to Monterey Road
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | October 2023 | Actual |
|---|---|---|
| Award | October 2025 | Actual |
| Construction start | April 2026 | Actual |
| Beneficial use | December 2026 | Scheduled |
Senter Road Bus Accelerated Infrastructure Delivery (BusAID)
Protected intersections, bus bulb outs and shelters at four Senter Road intersections.
- Design
- Bid & Award
- Construction
- Estimate
- $4.2M
- Starts
- Sep 2027
- Finish
- Jun 2028
Districts 2, 7
Project details
Latest update
City staff is preparing the 100% plans, specifications and estimate. Design is scheduled to finish in mid November, with the project advertised for procurement soon after.
About the project
Funded through the MTC Bus Accelerated Infrastructure Delivery (BusAID) Program. The work provides traffic safety improvements at Needles Drive, Lewis Road, Singleton Road and San Gregorio Way, including protected intersections with raised bikeways, bus bulb outs, traffic signal modifications, lighting upgrades and bus shelters. All work will be done in City of San José right of way.
Location
Senter Road at Needles Drive, Lewis Road, Singleton Road and San Gregorio Way
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | January 2025 | Actual |
|---|---|---|
| Design completion | November 2026 | Scheduled |
| Award | May 2027 | Scheduled |
| Construction start | September 2027 | Scheduled |
| Beneficial use | June 2028 | Scheduled |
Story Keyes Complete Streets Improvements
Raised bikeways, protected intersections and transit islands on Keyes Street and Story Road from 3rd Street to King Road.
- Design
- Bid & Award
- Construction
- Estimate
- $28.5M
- Starts
- Mar 2028
- Finish
- Nov 2028
Districts 3, 5, 7
Project details
Latest update
The project scope is being developed and is expected to be complete in September 2026. Design begins once the scope is confirmed.
About the project
Implements raised bikeways, protected intersections, transit boarding islands, wayfinding, micromobility stations, green stormwater infrastructure and pedestrian scale lighting on Keyes Street and Story Road from 3rd Street to King Road. The corridor serves a regional commercial hub and multiple Metropolitan Transportation Commission Priority Development Areas. The project connects with adjacent roadway projects and supports the Vision Zero goal of reducing traffic fatalities and severe injury crashes.
Location
Keyes Street and Story Road from 3rd Street to King Road
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | September 2026 | Scheduled |
|---|---|---|
| Design completion | June 2027 | Scheduled |
| Award | October 2027 | Scheduled |
| Construction start | March 2028 | Scheduled |
| Beneficial use | November 2028 | Scheduled |
Tamien Transportation Improvements
Class IV protected bike lanes along Lelong Street and West Alma Avenue.
- Design
- Bid & Award
- Construction
- Estimate
- $605,000
- Starts
- Aug 2027
- Finish
- Aug 2027
Districts 3, 7
Project details
Latest update
Design is 65% complete and scheduled to finish in December 2026. The project is tentatively scheduled to be advertised for bids in January 2027.
About the project
Creates Class IV protected bike lanes by installing dowelled in concrete separators and flexible delineators along Lelong Street and W. Alma Avenue.
Location
Lelong Street from Willow Street to W. Alma Avenue. W. Alma Avenue from Lelong Street to Vine Street.
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | October 2025 | Actual |
|---|---|---|
| Design completion | January 2027 | Scheduled |
| Award | April 2027 | Scheduled |
| Construction start | August 2027 | Scheduled |
| Beneficial use | August 2027 | Scheduled |
Tully Road, Rigoletto Drive and Brahms Avenue Streetlighting
New and upgraded streetlights at locations with documented safety concerns.
- Design
- Bid & Award
- Construction
- Estimate
- $110,000
- Starts
- Jul 2027
- Finish
- Aug 2027
District 7
Project details
Latest update
Staff is developing the Memorandum of Performance and the 95% design.
About the project
At Rigoletto Avenue and Brahms Avenue, a recent fatality reviewed by the Department of Transportation's Fatality Review Board led to a recommendation for additional lighting. At Tully Road and La Ragione Avenue near Coyote Creek, four fatalities over the past ten years led the Pedestrian Safety Team to prioritize the site for better illumination. The project installs a new streetlight at the intersection and replaces existing luminaires.
Location
Intersection of Rigoletto Drive and Brahms Avenue. Tully Road on both sides leading to Coyote Creek.
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | June 2026 | Actual |
|---|---|---|
| Design completion | October 2026 | Scheduled |
| Award | January 2027 | Scheduled |
| Construction start | July 2027 | Scheduled |
| Beneficial use | August 2027 | Scheduled |
Bridges
Structural repairs to bridges and overcrossings.
Tully Road Bridge over Coyote Creek Repair (Bridge 37C0142)
Sink hole repairs and a new asphalt overlay on the Tully Road bridge.
- Design
- Bid & Award
- Construction
- Contract
- $695,797
- Starts
- Oct 2026
- Finish
- Dec 2026
District 7
Project details
Latest update
The contract was executed on May 28, 2026. City staff is working with the contractor on submittals, and construction is anticipated to start in late October 2026.
About the project
Sink hole cavity repairs on the west side of the bridge, along with compaction grouting, controlled density fill backfills, subsurface drainage behind the abutments and a hot mix asphalt overlay.
Location
Tully Road bridge over Coyote Creek (Bridge No. 37C0142)
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | March 2025 | Actual |
|---|---|---|
| Design completion | February 2026 | Actual |
| Award | April 2026 | Actual |
| Construction start | October 2026 | Scheduled |
| Beneficial use | December 2026 | Scheduled |
Capitol Expressway Overcrossing Repair (Bridge 37C0721)
Concrete repairs at the Capitol Expressway overcrossing at Monterey Road.
- Design
- Bid & Award
- Construction
- Estimate
- $790,000
- Starts
- Aug 2027
- Finish
- Jan 2028
Districts 2, 7
Project details
Latest update
The consultant is working on the 100% plans, specifications and estimate. Design is expected to finish by the end of 2026.
About the project
Repair of concrete spalls on the bridge substructures (bents) and slope paving in front of the abutment of the existing Capitol Expressway Overcrossing at Monterey Road.
Location
Capitol Expressway overcrossing at Monterey Highway (Bridge No. 37C0721)
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | May 2026 | Actual |
|---|---|---|
| Design completion | January 2027 | Scheduled |
| Award | April 2027 | Scheduled |
| Construction start | August 2027 | Scheduled |
| Beneficial use | January 2028 | Scheduled |
Stormwater and Sewer
Stormwater capture and sanitary sewer rehabilitation.
Miscellaneous Sanitary Sewer Repairs FY 2024–2025, Package III
Sewer pipe replacement and lining on Stockton Ave, Almaden Rd, Hillsdale Ave and Old Tully Rd.
- Design
- Bid & Award
- Construction
- Contract
- $870,419
- Starts
- Oct 2026
- Finish
- Apr 2027
Districts 6, 7, 9
Project details
Latest update
Material submittals are being reviewed and the project is 45% complete. Construction begins in late October.
About the project
Developed from sanitary sewer overflow issues and video inspections showing severe pipe defects, to help reduce the City's sanitary sewer repair backlog. Work includes replacing and installing 6 inch and 10 inch vitrified clay pipe, lining about 305 feet of 6 inch pipe with cured in place pipe, replacing 5 existing manholes, building 4 new manholes, rehabilitating 5 manholes, point repairs, abandoning about 1,857 feet of 10 inch pipe, and reconnecting active sewer service laterals.
Location
Stockton Avenue, Almaden Road, Hillsdale Avenue and Old Tully Road
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | January 2026 | Actual |
|---|---|---|
| Design completion | May 2026 | Actual |
| Award | August 2026 | Actual |
| Construction start | October 2026 | Scheduled |
| Beneficial use | April 2027 | Scheduled |
Cast Iron Sewer Replacement FY 2024–2025, Package I
Replacing corroded 1950s cast iron sewer mains in neighborhoods across Districts 2, 7 and 10.
- Design
- Bid & Award
- Construction
- Contract
- $757,312
- Starts
- Oct 2026
- Finish
- Mar 2027
Districts 2, 7, 10
Project details
Latest update
Material submittals are being reviewed and the project is 40% complete. Construction begins in mid October.
About the project
Part of the Cast Iron Pipe Replacement Program, which replaces unlined cast iron sewer mains that have corroded significantly since their installation in the 1950s. The project removes about 146 feet of corroded cast iron pipe and replaces it with epoxy lined ductile iron pipe, installs about 3,080 feet of cured in place liner in existing 6 inch and 8 inch sewer pipe, and builds one manhole and one drop manhole connection. Service laterals are evaluated, repaired, reinstated and reconnected.
Location
Dawnbrook Court, Meridian Avenue, Vargas Drive, Vargas Court, Recife Way, Pilar Court, Porto Alegre Drive, Thorntree Drive, Thorntree Place, Antigua Drive and Starwood Place
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | August 2025 | Actual |
|---|---|---|
| Design completion | May 2026 | Actual |
| Award | July 2026 | Actual |
| Construction start | October 2026 | Scheduled |
| Beneficial use | March 2027 | Scheduled |
Sanitary Sewer Repairs FY 2025–2026, Package V
Point repairs and lining of about 4,800 feet of sanitary sewer mains.
- Design
- Bid & Award
- Construction
- Contract
- $786,783
- Starts
- Oct 2026
- Finish
- Mar 2027
Districts 4, 5, 7, 8
Project details
Latest update
A preconstruction meeting is targeted for early October 2026, and construction is anticipated to begin in late October 2026.
About the project
Part of the City's Exfiltration Abatement Program, which addresses maintenance concerns on sanitary sewer mains located above or crossing over storm drain mains, or within 10 feet laterally of them. The project performs point repairs on about 4,800 feet of existing 6, 8 and 10 inch mains, then rehabilitates all of the mains with a cured in place pipe liner.
Location
Christopher St, Naida Ave, Simon Ave, Norvella St, Caracas Ct, Bayhaven Dr, Waverly Ave, Mendota Way, Karl St, Terilyn Ave, Cunningham Ave, Elvira Ct, Kennedy Ave, Vista Oak, Piedmont Rd and Whitman Way
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | January 2026 | Actual |
|---|---|---|
| Design completion | March 2026 | Actual |
| Award | July 2026 | Actual |
| Construction start | October 2026 | Scheduled |
| Beneficial use | March 2027 | Scheduled |
Kelley Regional Stormwater Capture
A stormwater basin along Coyote Creek and Roberts Avenue to treat runoff.
- Design
- Bid & Award
- Construction
- Estimate
- $8.6M
- Starts
- May 2027
- Finish
- Feb 2028
District 7
Project details
Latest update
Plans and specifications are with internal reviewers for signatures, which are expected to be complete in mid October 2026.
About the project
An approximately 5.64 acre site in Southeast San José along Coyote Creek and Roberts Avenue. The project installs a stormwater basin to treat runoff, along with fencing, a gate, storm drain pipes, a storm drain manhole and a bioretention basin.
Location
Along Coyote Creek and Roberts Avenue in Southeast San José
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | April 2024 | Actual |
|---|---|---|
| Design completion | November 2026 | Scheduled |
| Award | March 2027 | Scheduled |
| Construction start | May 2027 | Scheduled |
| Beneficial use | February 2028 | Scheduled |
Miscellaneous Sanitary Sewer Repairs FY 2026–2027, Package I
Sewer repairs near North Capitol Ave, Mueller Ave, San Fernando St, McLaughlin Ave and Schrader Dr.
- Design
- Bid & Award
- Construction
- Estimate
- $1.3M
- Starts
- Mar 2027
- Finish
- Jul 2027
Districts 3, 4, 5, 7, 9
Project details
Latest update
Public Works is finalizing the design, which is expected to be complete by October 2026.
About the project
Evaluates the condition of five selected 6, 8 and 12 inch vitrified clay pipe segments totaling about 955 feet. Work includes about 61 feet of point repairs, jack and bore installation of 92 feet of 6 inch HDPE pipe, new and rehabilitated manholes, replacement of about 575 feet of 6 inch pipe, 288 feet of cured in place liner, and reinstatement of sewer laterals.
Location
North Capitol Avenue, Mueller Avenue, San Fernando Street, McLaughlin Avenue and Schrader Drive
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | July 2026 | Actual |
|---|---|---|
| Design completion | November 2026 | Scheduled |
| Award | January 2027 | Scheduled |
| Construction start | March 2027 | Scheduled |
| Beneficial use | July 2027 | Scheduled |
Sanitary Sewer Condition Assessment FY 2026–2027, Package II
Cleaning and inspecting large sanitary sewer mains to guide future repairs.
- Design
- Bid & Award
- Construction
- Estimate
- $1.2M
- Starts
- Jun 2027
- Finish
- Oct 2027
Districts 3, 6, 7
Project details
Latest update
The project is 20% designed. Design is expected to finish in December 2026.
About the project
Cleans and assesses the condition of about 463 feet of 33 inch, 772 feet of 36 inch, 3,875 feet of 42 inch and 2,067 feet of 48 inch sanitary sewer mains. The data feeds the Sanitary Sewer Engineering Section's Info360 Asset database for future project scoping. All CCTV inspections follow the NASSCO Pipeline Assessment Certification Program, and SONAR inspections are used during extreme conditions.
Location
Millpond Dr, Winepol Loop, Curtner Ave, Stone Ave, Cimino St, N 9th St, S 9th St, Sharks Way, Terraine St, Bassett St, and along easements
Location map
Map from the City of San José CIP report.
Schedule
| Scope completion | July 2026 | Actual |
|---|---|---|
| Design completion | December 2026 | Scheduled |
| Award | March 2027 | Scheduled |
| Construction start | June 2027 | Scheduled |
| Beneficial use | October 2027 | Scheduled |
No projects match. Try a different phase, type or search.
Source: City of San José Department of Public Works, Capital Improvement Program report for District 7, updated September 24, 2026. Page updated September 28, 2026. Dates and costs are subject to change. Costs are the construction contract amount once awarded, otherwise the engineer’s estimate.